This week we have had good progress with the drains all in, painting outside finished for the moment, gibbing completed inside ready for the plastering and stopping, some electrics installed and the polished concrete floors in.


Here you can see the drains being dug and laid around the front and down the side of the house.


This is the water lille sump which collects the water from the bathrooms and pumps it into the irrigation field that is going to be installed under the lawn.


All the gibbing completed in the family and dining room. Starting to show the effect of the chapel ceiling and the kitchen area.


The excellent view out of the lounge windows. Great place to just sit and look across the harbour.


Visited on Thursday to find a team of eight painters painting the outside of the house. They has the second coat on by lunch time and then left. They will be back for the inside and will complete the little bits and pieces still not finished on the outside. Note still a couple of weather boards to install in the entrance way.


Special power generator for the machinery needed for the cutting and polishing of the floors in the kitchen, entrance way, laundry and bathrooms.  - see special page on concrete polishing.


Next week we will have the garage door in, all internal doors, plastering completed and they should be starting to paint inside.
The deck will probably also be started by the end of the week.
Still on target for the 16th December move in.