Friday 28 October 2011

Rain and Wind!!!

Another frustrating week, albeit a short week because of Labour day. Tuesday was high winds, Wednesday wind and rain, Thursday misty rain for part of the day and Friday misty rain all day.

Hence very little of the roof has been done, the windows have been put on hold until next week and the weatherboards could only be installed up to where the safety rail for the roofers starts.


The only part of the roof that has been installed is over the garage - it better be fine next week...


The weather boards have been installed right around the house up to just above the windows, so the installation should be completed quite quickly once the roof is completed.


Nearly all the decisions for the inside have now been made with LED lights selected, colour schemes completed, wiring for electrics etc... and security system. So next week should be a big week with the insulation and electrics being completed along with the plumbing, roof, windows, doors and weatherboards.

Or are we dreaming?