Wednesday 21 September 2011

Lots of Action

Now that the concrete has cured there has been a lot of action in today, Wednesday 21 September.

First the areas that are going to be polished concrete have had their first cut and will now sit waiting for the final polishing once the walls are up. Here we have Jake Currie from BM Scott Ltd on the cutting tool using the Husqvarna Construction approach or HiPERFLOOR



On the same day the precut wall and roof sections arrive just as the contractor is completing the burying of the 4500L rain harvesting tank.


The balance of the walls are stacked across the road ready for installation tomorrow. The construction is expected to be all up in one day. Margaret pleased to see the walls and ceilings all on site.
We are still on track to complete the build by early December.




The 4500 L tank is buried in the ground with the top cover all that can be seen above the ground. The cover is in the front garden and will be surrounded by plants while the rest of the tank which goes out toward the retaining wall will be lawn. See the page tab for information on the rain water harvesting and water lillie systems being installed.