The fences and side gates are now installed and the letterbox is up.
I have been very busy over the holidays with the landscaping and now have the gardens near finished and the Japanese garden in the front all formed and ready to have the solar water pump installed. The extra mowing strip on the road reserve has also been finished and the lawn has been oversown again now that its at the right level.
Japanese garden with three Acers, ground covers and mosses, two creeks and three ponds nearly ready. Still needs solar water pump to be installed and the sealant for the ponds to be applied.
Mowing strips for the road reserve lawn completed.
Trees at the top include Kowhai and Lancewood
lawn oversown and should be up by end of the month.
Side fence now all complete and the gardens starting to come away.
Side gates installed down this side of the house and beside the garage.
Five old rose types planted all have great smells.